Careful planning is the key to the successful delivery of your item. Timing is critical. Below is a guide to some fundamental timing issues to be aware of.
Permit Applications
If the load you are looking to transport is oversize there is a good chance that it will require permits for movement. When it comes to booking transport allowance needs to be made for the time required for the permit process. This varies according to the size and weight of the item that is required for transit.
A handy rule of thumb for the time frame required for the formal permit process to allow access for oversize vehicles is as follows:
|
Load Weight |
20 to 50 ton |
24 hrs from Booking |
|
Load Weight |
50 to 65 ton |
24 - 48 hrs from Booking |
|
Load Weight |
65 to 100 ton |
48 - 96 hrs from Booking |
|
Load Weight |
100 to 125 ton |
4 - 7 days from Booking |
|
Load Weight |
125 to 200 ton |
7 - 14 days from Booking |
|
Load Weight |
2.5m Wide to 4.5m Wide |
24 hrs from Booking |
|
Load Weight |
4.5m Wide to 8.5m Wide |
3 - 5 days from Booking |
|
Load Height |
3m High to 3.9m High |
24 hrs from Booking |
|
Load Height |
3.9m High to 4.4m High |
48 - 72 hrs from Booking |
|
Load Height |
4.4m High to 8m High |
7 - 14 Days from Booking |